AI rack pilot sourcing sprint

Quote comparison

Decision memo

Part-specific sourcing decision

91/100 top score

Primary

Rack frame: Taichung Thermal Systems

Secondary

Cooling/manifold: Ohio Rapid Sheet Metal

Backup

Domestic validation: Ohio Rapid Sheet Metal

Current blocker

Landed-cost assumptions, packaging dimensions, and final certification evidence are still missing.

Next action

Request freight, tariff/import, packaging, and Incoterm clarification before sample commitment.

Taichung Thermal Systems

Taiwan

91
Capability15/15
Price30/30
Lead time10/20
Compliance15/15
Region risk7/10
Logistics5/8
Communication6/8
Trust6/8

Ohio Rapid Sheet Metal

United States

82
Capability15/15
Price9/30
Lead time20/20
Compliance11/15
Region risk10/10
Logistics8/8
Communication6/8
Trust6/8

Pearl River Rack Systems

China

77
Capability15/15
Price13/30
Lead time13/20
Compliance15/15
Region risk7/10
Logistics5/8
Communication7/8
Trust8/8
SupplierCountry/RegionUnit priceToolingMOQLead timeIncotermPayment termsTariff/Import RiskLogistics RiskGeopolitical RiskDual-source FitCertificationsRisksScoreRecommendation
Taichung Thermal SystemsTaiwan$96.00$1202024 daysFOB Kaohsiung30/70mediummediummediumsecondaryISO 9001, RoHS
Frame would be outsourcedPressure rating must be confirmed
91/100Strong secondary supplier for cooling subassembly and regional optionality.
Ohio Rapid Sheet MetalUnited States$310.00$0412 daysFCA OhioNet 30 after sample approvallowlowlowbackupISO 9001
Higher unit costPilot capacity must be reserved
82/100Recommended backup for fast validation, nearshore resilience, and tariff risk reduction.
Pearl River Rack SystemsChina$113.50$01018 daysEXW50/50highmediummediumprimaryISO 9001, RoHS
EXW excludes freightLoad rating certificate not attachedTariff exposure requires landed-cost review
77/100Best cost-speed fit for rack frame; pair with a lower-risk regional backup.
Lowest unit price

$42.00

Fastest lead time

12d

Risk flags

7

Negotiation points

4

SupplierCountry/RegionItemUnit priceMOQLead timeSampleToolingNotes
Pearl River Rack SystemsChina42U server rack frame$1851018 days$220$0Custom depth available; packaging not yet specified.
Pearl River Rack SystemsChinaPerforated front and rear doors$421018 days$60$0Black powder coat included.
Taichung Thermal SystemsTaiwanLiquid cooling manifold kit$962024 days$130$120Includes pressure test report after sample.
Ohio Rapid Sheet MetalUnited States42U server rack frame$310412 days$340$0Best for prototype validation and tariff-free domestic backup.

Taichung Thermal Systems score breakdown

Total: 91/100
Capability fit: 15/15
Price competitiveness: 30/30
Lead time: 10/20
Quality/compliance: 15/15
Region/geopolitical risk: 7/10
Logistics risk: 5/8
Communication quality: 6/8
Trust/relationship: 6/8
Scalability: 4/6
Risk penalty: -8

Ohio Rapid Sheet Metal score breakdown

Total: 82/100
Capability fit: 15/15
Price competitiveness: 9/30
Lead time: 20/20
Quality/compliance: 11/15
Region/geopolitical risk: 10/10
Logistics risk: 8/8
Communication quality: 6/8
Trust/relationship: 6/8
Scalability: 4/6
Risk penalty: -8

Pearl River Rack Systems score breakdown

Total: 77/100
Capability fit: 15/15
Price competitiveness: 13/30
Lead time: 13/20
Quality/compliance: 15/15
Region/geopolitical risk: 7/10
Logistics risk: 5/8
Communication quality: 7/8
Trust/relationship: 8/8
Scalability: 6/6
Risk penalty: -12

Taichung Thermal Systems

Recommended as the current primary source based on weighted score and execution fit.

91/100

Why not the default

Do not proceed without resolving risk flags and landed-cost assumptions.

Negotiation questions

  • - Can you confirm landed cost assumptions and Incoterm options?
  • - Can you provide certification and QC evidence before sample PO?
  • - What changes at prototype, pilot, and production volumes?

Ohio Rapid Sheet Metal

Useful as a secondary or backup source for dual-source resilience.

82/100

Why not the default

Not the primary recommendation because the total score is lower or the scope fit is narrower.

Negotiation questions

  • - Can you confirm landed cost assumptions and Incoterm options?
  • - Can you provide certification and QC evidence before sample PO?
  • - What changes at prototype, pilot, and production volumes?